One Day's Work and the LCM Method
- A job done in n days means of it a day, and in d days.
- LCM method: total work = LCM of the times; each person's units a day = LCM ÷ own time.
- A in 25 days, B in 100: work 100 units, A does 4 a day and B 1, so 5 together and 20 days.
- Part of a job: in 4 days means the whole job in 14.
- Trap: never add or average times. Add rates.
Two and Three People Together
- Two people: .
- One person from the pair: . A and B in 24 days, A alone in 40: , so B takes 60 days.
- Three people: add three rates. 30, 45 and 90 days: work 90 units, 3 + 2 + 1 = 6 a day, so 15 days.
- is for two people only; for three, use units.
- Together is always quicker than the fastest person alone. Use that to strike out options.
Pair Data: A + B, B + C, C + A
- Add the three pair rates and halve: that is all three together.
- One person = all three − the other two.
- A + B in 20 days, B + C in 28, C + A in 35: work 140, pairs 7, 5 and 4 a day. All three = 16 ÷ 2 = 8 a day, so days. C = 8 − 7 = 1 a day, 140 days.
- Trap: forgetting to halve gives half the true time.
Efficiency and Time
- Time runs the other way to efficiency: .
- A is x% more efficient than B: A : B = (100 + x) : 100, times the other way. 40% more: 7 : 5, so times 5 : 7; B 35 days, A 25.
- Half as much work a day means twice the time.
- Ratio with joint time: work = ratio sum × days. 2 : 5 together in 10 days: work 70, A alone 35.
- Trap: 25% more efficient cuts the time by 20%, not 25%.
Leaving and Joining
- Add the work stretch by stretch: (rate of those working) × days.
- Leaves after n days: together n days, then the rest alone.
- Leaves k days before the end: call the total T and give that person T − k days. A in 36 days, B in 54, A leaves 4 days early: 3(T − 4) + 2T = 108, so T = 24.
- Joins later: the starter works the whole time.
- Trap: the total time and the time after the change are both in the options.
Men-Days Chain Rule
- : more men or hours, fewer days; more work, more days.
- 21 men, 10 days, 8 hours a day for one wall. Two walls, 28 men, 6 hours: = 20 days.
- Midway change: work left = total − done, divided by the new team.
- On time: men needed = work left ÷ days left; extra = needed − present.
- Trap: the question usually wants the extra men.
Men, Women and Children
- Turn everyone into one unit. 3 men or 5 women: 1 man = women.
- 4 men or 6 women in 21 days: work 126 woman-days. 2 men + 9 women = 12 women, so days.
- Two mixed groups doing the same job: set the two work totals equal to get the ratio.
- Per person: 6 men in 11 days means 1 man in 66.
- Trap: a man and a woman are not equal workers unless the question says so.
Alternate Days and Helpers
- Find one round (2 days for A and B in turns, 3 days for a helper every third day) and its units.
- Run whole rounds, then go day by day; the last day can be a part day.
- A in 9 days, B in 24, on alternate days: work 72, a round gives 11. A first: 66 after 12 days, and day 13 needs 6 of A's 8, so days. B first: days.
- Trap: (work ÷ round) × round length fails when the last round is cut short.
Negative Work
- A breaker has a minus sign: net = builder − breaker.
- Builder 7 days, breaker 12, at once: , so days.
- On alternate days the job ends on a builder's day. Builder first: wall 84 units, +12 then −7, so +5 a round. After 15 rounds (30 days) it has 75; day 31 needs 9 of his 12, so days.
- Trap: 84 ÷ 5 rounds × 2 days = days overshoots.
Work and Wages
- Pay is shared in the ratio of work done, never of days or times.
- Same days together: ratio of efficiencies, the inverse of times. 16 and 40 days give 5 : 2, so ₹3,500 splits as ₹2,500 and ₹1,000.
- Different days: each person's work = rate × days worked, and the share is that fraction of the pay.
- A helper's share = the part of the job the others left for him.
- Trap: splitting in the ratio of times swaps the shares.
Pipes as Signed Rates and Leaks
- Inlet +, outlet or leak −. Time = tank ÷ net rate.
- Fills in 21 hours, empties in 70: , so 30 hours.
- Leak found late: a hours without it, b hours with it, so the leak alone takes . 4 hours becoming 4 hours 48 minutes gives 24 hours.
- Part-full tank: part to fill ÷ net rate.
- Trap: product ÷ sum is for two filling pipes; product ÷ difference is for a pipe against a leak.
Pipes Opened or Closed at Different Times
- Go stretch by stretch: (rate of the open pipes) × time.
- Closed after t hours: both for t hours, then the other pipe alone.
- Opened later: the first pipe runs alone first; count from the first opening unless told otherwise.
- Closed so the tank fills in T hours: the pipe left open runs all T. A 16 hours, B 20, full in 15: , so A ran 4 hours.
- Trap: the total and the time after the change both appear as options.
Alternate Hours
- One round = one hour of each pipe in turn. Count the units each round adds.
- Two inlets: run whole rounds, then hour by hour; the last hour can be a part hour.
- Inlet and outlet in turns (the last-hour trap): the tank fills during an inlet hour. Inlet 3 hours, outlet 8: tank 24 units, +8 then −3. After 4 rounds (8 hours) the tank has 20, and hour 9 needs only 4 of the inlet's 8. Answer hours, not .
- Trap: tank ÷ gain per round × 2 overshoots.
Capacity in Litres
- Put every flow in one unit (litres a minute or an hour) before mixing it with fractions of the tank.
- Capacity = litres ÷ fraction. Outlet 8 litres a minute; inlet fills in 4 hours; both open, 6 hours. Outlet = of the tank an hour = 480 litres, so 5,760 litres.
- Pipes d litres a minute apart, taking a and b minutes (a > b): capacity = .
- Trap: litres a minute against hours.